Production

Designers and the shop share one building: the stress engineer sees the product in assembly, and the process engineer joins from the first sketch.

24 m
assembly bay span, two 32 t overhead cranes
50 mm
thickest plate our rolls take at 3,000 mm width
25 MPa
highest hydraulic test pressure on our test bench
100 %
of shell welds radiographed or ultrasonically tested by our own laboratory

From specification to shipment: 18⁠–⁠40 weeks

0481216202428323640weeksSpecification and calculation2⁠–⁠4 weeksshortest: 0–2longest: 0–4Design documents and approval4⁠–⁠8 weeksshortest: 2–6longest: 4–12Metal and components6⁠–⁠12 weeksshortest: 4–10longest: 8–20Manufacture and inspection8⁠–⁠16 weeksshortest: 9–17longest: 22–38Tests, documents, shipment1⁠–⁠2 weeksshortest: 17–18longest: 38–40shortest — 18 weekslongest — 40 weeks
shortestlongest
The same as a table
Stageshortestlongest
Specification and calculation0–20–4
Design documents and approval2–64–12
Metal and components4–108–20
Manufacture and inspection9–1722–38
Tests, documents, shipment17–1838–40

We order metal while drawings are being approved, so the stages partly overlap.